Aftersales services for customers
Many former customers are thankful for and appreciative of our 1Z0-244 exam materials. We always offer assistance to our customers when they need us and offer our help 24/7. The most important is our employees are patient to deal with your need about 1Z0-244 learning materials: Oracle EBS R12: Advanced Supply Chain Planning at any time. They always treat customers with curtesy and respect. So you can contact with us if you have problems. There are so many former customers who appreciated us for clear their barriers on the road, we expect you to be one of them and pass the test like a piece of cake. Our 1Z0-244 actual lab questions can help you practice & well prepare for your test so that you can pass real exam easily. So do not need to hesitate and purchase our Oracle EBS R12: Advanced Supply Chain Planning study materials, you will not regret for it.
It is a lifetime study time. The society advocates us to further our study and improve working skills at every aspect. For exam candidates like you it is of great importance to pass the Oracle exams effectively. That is why we offer you the excellent 1Z0-244 learning materials: Oracle EBS R12: Advanced Supply Chain Planning compiled by professional experts. Now, let us take a comprehensive look of the features of the 1Z0-244 actual lab questions as follow:
Great exam materials for customers
We have been trying to win clients' affection by our high quality 1Z0-244 learning materials: Oracle EBS R12: Advanced Supply Chain Planning and we realized it in reality. So they affirm that our 1Z0-244 exam resources are professional in quality and responsible in service. If you are afraid to trying, you may lose the chance to accept the excellent 1Z0-244 actual lab questions and pass exam smoothly. If you blindly choose the practice test questions on the market, you may need to start to prepare the test afresh. So the former customers are agreeable to the quality of our exam materials edited by experts elaborately, and you can trust us that our 1Z0-244 practice test: Oracle EBS R12: Advanced Supply Chain Planning are an effective aid for your exam.
Our exam materials can be trusted
We have been collecting the important knowledge into the 1Z0-244 learning materials: Oracle EBS R12: Advanced Supply Chain Planning over ten years and the progress is still well afoot. So it is a best way for you to hold more knowledge of the 1Z0-244 actual lab questions. Owing to our special & accurate information channel and experienced education experts, our 1Z0-244 exam preparation get high passing rate and can be trusted. By spending up to 20 or more hours on our 1Z0-244 certification training questions, you can clear exam surely. About the updated versions, we will send them to you instantly within one year, so be careful with your mailbox.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Oracle 1Z0-244 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Plan Analysis and Execution | - Planner Workbench usage
|
| Topic 2: Supply Planning and Optimization | - Advanced Supply Chain Planning optimization
|
| Topic 3: Advanced Supply Chain Planning Concepts | - ASCP architecture and components
|
| Topic 4: Demand Planning and Forecasting | - Forecast generation and consumption
|
Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
End Item A can be substituted with End Item B and End Item B can be substituted with End Item
C. The effective dates for these substitutions are given in the Exhibit.
Which three statements are correct?
- A. Plan your entire horizon in daily buckets to improve performance.
- B. The inferred substitution rule between Item A and C is effective from 06-JAN-2008 to 22- JAN-2008.
- C. If End Item A is requested, it can be satisfied with the supplies from End Items A or B or C.
You anticipate having a very large plan with many Items, Purchase Orders, and Sales Orders.
You want to plan at a detailed Item level as much as possible, but detailed Resource planning Is less Important.
Because your enterprise Is global. It Is Important to have the plan run In the shortest possible time.
Identify two aggregation settings that will help you achieve your goals. - D. End Item A substitution with End Item C is not possible.
- E. The inferred substitution rule between Item A and C is effective only from 06-JAN-2008 to 10- JAN-2008.
- F. Plan your entire horizon in weekly buckets.
- G. End Item A substitution with End Item C Is Inferred.
- H. Plan at the Item level In the short range and Product Family level in the long range.
- I. Plan Individual Resources In the short term and aggregate Resources in the longer term buckets.
Correct Answer: B,D 🗳️
Exhibit.
In a manufacturing environment where Oracle Shop Floor Management Is used, the production process with Information about Yield (Yld), Net Planning Percent (NPP), Cumulative yield (CY), Reverse Cumulative Yield (RCY) is displayed for a product.
If the order quantity is 100, what is the raw material quantity and resource requirement ASCP will schedule respectively at operation sequence 10?
- A. Raw material qty 98 and resource requirement for 98
- B. Raw material qty 97.37 and resource requirement for 117.63
- C. Raw material qty 100 and resource requirement for 100
- D. Raw material qty 113.63 and resource requirement for 113.63
- E. Raw material qty 117.63 and resource requirement for 113.63
Correct Answer: C 🗳️
Your client currently has two manufacturing plants, plants, four Inventory locations, and one distribution center. When doing the future state analysis, the Operations Directory at the client site said that they have expansion plans after the go-live of the current Oracle in Implementation. They plan to add 10 more distribution centers and these can be transfer of goods between any two distribution centers. Each distribution center would need to optimize its inventory level and forecasts will be handled in Demand Planning for better customer satisfaction.
The client IT Manager proposes to use one main inventory Organization to represent all the facilities and use sub inventories to represent the various inventory locations in the manufacturing plant and the distribution center. The future distribution centers can be modeled as subinventories because Oracle allows you to define a large number of subinventories. From the system point of view, It will be easier to maintain and inventory transfers between sub inventor using Move Orders are possible.
Select three correct statements about the above scenario.
- A. You design the same way and you also add more transaction types to take care of future transfers between any two distribution centers.
- B. You design multiple inventory Organizations to model this so that in future when the client needs to plan a transfer from one facility to another, ASCP will be able to suggest such a transfer.
- C. You design the same way as the client IT Manager because It will fulfill all the requirements of the client.
- D. Inventory Optimization does not calculate safety stock at the subinventory level. So the client needs multiple inventory Organizations.
- E. Global Order Promising can calculate availability at the subinventory level, so you need one inventory Organization with multiple subinventories.
- F. Demand Planning forecasts by Organization, not by subinventory. So the client needs multiple inventory Organizations.
Correct Answer: A,B,D 🗳️
Which are the four pegging modes available for a user to set up in combination with the MSC: Use FIFO Pegging profile option?
- A. Priority
- B. Priority/FIFO
- C. Hard Pegging
- D. Soft Pegging
- E. Standard
- F. End Assembly Pegging
- G. FIFO
- H. End Assembly/Soft Pegging
Correct Answer: A,B,E,G 🗳️
End Item A can be substituted with End Item B and End Item B can be substituted with End Item
C. The effective dates for these substitutions are given in the Exhibit.
Which three statements are correct?
- A. End Item A substitution with End Item C is not possible.
- B. The inferred substitution rule between Item A and C is effective from 06-JAN-2008 to 22-JAN- 2008.
- C. The inferred substitution rule between Item A and C is effective only from 06-JAN-2008 to 10- JAN-2008.
- D. End Item A substitution with End Item C Is Inferred.
- E. If End Item A Is requested, it can be satisfied with the supplies from End Items A or B or C.
Correct Answer: B,C,D 🗳️
Viewing page 1 out of 18 pages.
Viewing questions 1-5 out of 90 questions.