[UPDATED May-2026] Best Value Available Preparation Guide for CTS-I Exam
1 Full CTS-I Practice Test and 480 Unique Questions, Get it Now!
AVIXA CTS-I Exam Certification Details:
| Schedule Exam | Pearson VUE |
| MemberExam Price | $475(USD) |
| Exam Code | CTS-I |
| Number of Questions | 110 |
| Sample Questions | AVIXA CTS-I Sample Questions |
| Non-Member Exam Price | $575(USD) |
| Books / Training | Candidate Handbook |
AVIXA CTS-I - Installation Exam Syllabus Topics:
| Topic | Weight |
|---|---|
| Duty A: Conducting Pre-Installation Activities | 20% |
| Task 1: Review Audiovisual Project Documentation | 4% |
| Task 2: Conduct Technical Site Survey | 4% |
| Task 3: Prepare for Audiovisual Installation | 4% |
| Task 4: Evaluate Overall Facility Readiness | 4% |
| Task 5: Conduct On-Site Preparations for Installation | 4% |
| Duty B: Conducting Site Rough-In/First-Fix | 10% |
| Task 1: Deinstallation of Existing Equipment and cabling | 2% |
| Task 2: Mount Substructure | 4% |
| Task 3: Pull Cable | 4% |
| Duty C: Installing Audiovisual Systems | 38% |
| Task 1: Assemble AV Rack | 4% |
| Task 2: Wire the AV Equipment Rack | 5% |
| Task 3: Distribute AV Equipment | 4% |
| Task 4: Mount AV Equipment | 4% |
| Task 5: Terminate Cables | 5% |
| Task 6: Configure Network Properties of Equipment | 4% |
| Task 7: Load Configuration and Control Programs | 4% |
| Task 8: Test the AV System | 4% |
| Task 9: Calibrate the AV System | 4% |
| Duty D: Perform Systems Close Out | 11% |
| Task 1: Demonstrate to Client or Client's Representative that System Performs to Specifications | 4% |
| Task 2:Provide Training on System Operation | 4% |
NEW QUESTION # 135
Checking an electrical system for a _____ should only be performed with the aid of a qualified electrician.
- A. Neutral/ground swap
- B. Hot/neutral swap
- C. Hot/ground swap
- D. Open ground-wiring error
Answer: A
NEW QUESTION # 136
Heat dissipated by equipment in an AV rack is measured in:
- A. BTU/H
- B. Coulombs
- C. Degrees
- D. Watts
Answer: A
NEW QUESTION # 137
When drilling is necessary, what is the purpose of pilot holes?
- A. To check for electrical wiring
- B. To assess the strength of the mounting material
- C. To wear out the smaller drill bits before the larger ones
- D. To give the screws direction
Answer: D
NEW QUESTION # 138
When should you run electrical and signal cables to a flat panel display?
- A. Before you've found all of the studs behind the mounting wall
- B. Once you've placed it upon a flat, clean, shipping blanket
- C. After it's been mounted to the wall
- D. After you've made final adjustments to the display based on the viewing environment
Answer: C
NEW QUESTION # 139
Which device provides a direct physical connection between multiple nodes?
Response:
- A. Router
- B. Gateway
- C. Bridge
- D. Switch
Answer: D
NEW QUESTION # 140
The point at which power enters a building is called the _____.
- A. hot spot
- B. facility drop
- C. service entrance
- D. demark
Answer: C
NEW QUESTION # 141
The most common type of Viewing Category is __________.
- A. Basic Decision Making (BDM)
- B. Analytical Decision Making (ADM)
Answer: A
NEW QUESTION # 142
The key elements of a project should be driven by:
- A. The deadline for completion
- B. The cost of materials
- C. The overall budget
- D. The client's need
Answer: D
NEW QUESTION # 143
Items which require user control should be placed in the _____ of the rack.
- A. Bottom
- B. very top
- C. back
- D. middle
Answer: D
NEW QUESTION # 144
The connector pictured below is known as:
Response:
- A. Insulation displacement
- B. Captive screw compression termination
- C. Direct connection termination
- D. Ancillary dimpled solder connection
Answer: B
NEW QUESTION # 145
If the projector you have to install is discontinued by the manufacturer, what should you do?
Select all that apply.
Response:
- A. Try to find the specific model through an online vendor
- B. Discuss the need for change with the AV designer and your project manager
- C. Install another similar model and record the model number on the project documentation
- D. Redline the change on the appropriate project document, send it to your project manager for submission of a formal RFI or RFC, and wait for a CO
Answer: B,D
NEW QUESTION # 146
What is a ground loop?
Response:
- A. An electrical connection between any grounded conductor and any non-current-carrying metal object
- B. A continuous isolation between receptacles and electrical circuits
- C. An interruption of a cable shield connection
- D. An electrically conductive area that has two or more ground reference connections
Answer: D
NEW QUESTION # 147
Before entering a construction site, safety coordination and requirements should be discussed with the:
- A. plumbing contractor
- B. electrical contractor
- C. general contractor
- D. network contractor
Answer: C
NEW QUESTION # 148
Oscillating symbol 'tilde' ~ with Resistor IMAGE
WHAT IS IS?
- A. DC Circuit
- B. AC Circuit
- C. Parallel Circuit
- D. Series Circuit
Answer: B
NEW QUESTION # 149
In a loudspeaker circuit, what color wire carries the negative (-) current?
- A. Red
- B. Grey
- C. White
- D. Black
Answer: D
NEW QUESTION # 150
What type of drawing view shows the layout of items on the ceiling?
Response:
- A. Elevation drawing
- B. Reflected ceiling plan
- C. Reflected floor plan
- D. Detail ceiling drawing
Answer: B
NEW QUESTION # 151
How would a commissioning technician establish substantial completion/practical completion?
- A. Generate a list of all damaged equipment, setting up the DSP
- B. Generate a punch or defects list, getting architects to sign off on repairs
- C. Complete a request for changes form, filing an RFQ
- D. Complete all preliminary tests, confirm systems installation and readiness for final test
Answer: D
NEW QUESTION # 152
Which of the following choices lists the correct pinouts for the T-568A end of a crossover network cable (pin
1-8):
- A. WGr, Gr, WOr, B, WB, Or, WBr, Br
- B. Gr, WGr, WOr, B, WB, Or, WBr, Br
- C. Br, WBr, Or, WB, B, WOr, GR, WGr
- D. WOr, Or, WGr, B, WB, Gr, WBr, B
Answer: A
NEW QUESTION # 153
Which of the following can be used to automatically turn off unused microphones?
- A. Absorbers
- B. filters
- C. gates
- D. limiters
Answer: C
NEW QUESTION # 154
Where should a line driver be installed?
- A. Near the destination
- B. By the source of the noise
- C. In the middle of the signal pathway
- D. Near the source
Answer: D
NEW QUESTION # 155
_____ draws the video image on the display in a sequence of lines from top to bottom.
Response:
- A. Frame rate
- B. Progressive scanning
- C. Interlaced scanning
- D. Refresh rate
Answer: B
NEW QUESTION # 156
A(n) _____ is a graphical representation of the microphone's directionality and electrical response characteristics.
- A. frequency response specification chart
- B. polar plot
- C. performance criteria circle graph
- D. electrical output level diagram
Answer: B
NEW QUESTION # 157
What is a characteristic of multimode fiber optic cables?
- A. Multimode uses yellow cable jackets
- B. Multimode cable does not have limited bandwidth
- C. Multimode cables send the signal quicker than single-mode cables
- D. Multimode disperses the signal into many light paths
Answer: D
NEW QUESTION # 158
For an ethernet cable (UTP) to meet certification standards, the maximum length is Response:
- A. 98, or 30m
- B. 492, or 150m
- C. 328, or 100m
- D. 984, or 300m
Answer: C
NEW QUESTION # 159
What is an advantage of using an adjustable ceiling mount support structure?
- A. Prevents a mount from separating
- B. Allows the set screws to stabilize
- C. Lowers the mount for easy projector maintenance
- D. Allows for flexibility in the location of the mount
Answer: D
NEW QUESTION # 160
......
Get Instant Access to CTS-I Practice Exam Questions: https://testinsides.vcedumps.com/CTS-I-examcollection.html
