NEW QUESTION 34
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Kanban
- B. Production order release
- C. Material requirements planning
- D. Backflushing
Answer: C
NEW QUESTION 35
In the Capacity Scheduling Table, which settings can you select for the planning strategy? Note: There are 3 correct answers to this question.
- A. Planning mode
- B. Direction
- C. Scheduling control
- D. Finiteness level
- E. Fixed pegging
Answer: A,B,C
NEW QUESTION 36
Which of the following is valid sequence of the main activities in production order processing?
- A. Creation, availability check, release, material widrawal, confirmation
- B. Creation, release, settlement, goods issue, confirmation, goods receipt
- C. Creation, release, printing, goods issue, confirmation, goods receipt
- D. Creation, printing, release, goods issue, confirmation, goods receipt
Answer: A,C
NEW QUESTION 37
What happens to this dependent requirement when you convert the planned order into a production order?
- A. They are converted into a reservation.
- B. They are converted into a production order.
- C. They are converted into a schedule line.
- D. They are converted into a planned order.
Answer: A
NEW QUESTION 38
For which categories can you define BOMs in SAP S/4HANA?
- A. Class
- B. Sales order
- C. Document Structure
- D. Work Center
Answer: B,C
NEW QUESTION 39
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
- A. Plant
- B. Work center
- C. Production version
- D. Material
Answer: B,D
NEW QUESTION 40
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?
- A. 100% check
- B. By usage probability
- C. Simultaneous
- D. First in first out (FIFO)
Answer: A,B
NEW QUESTION 41
What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?
- A. Material Requirements Planning (MRP)
- B. Demand Planning (DP)
- C. Supply Network Planning (SNP)
- D. Capacity Requirements Planning (CRP)
Answer: A
NEW QUESTION 42
In your plant, MRP is activated.
Which option do you have to exclude a materila from the MRP run?
- A. Use a specific material group
- B. Use a specific material status
- C. Use a specific MRP type
- D. Use specific MRP controller
Answer: A,D
NEW QUESTION 43
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
- A. Use heuristic.
- B. Use a planning group.
- C. Use a resource group.
- D. Use a propagation range.
Answer: A
NEW QUESTION 44
You want to set up a make-to-order planing scenario for finished material. The bil of material contains two components: one should be procured for each sales order individually, the other one shold be procured jointly for all independent requirements. Forcasting for the finished product is NOT possible. Which setting do you make to achive this?
- A. Choose planning strategy 20 (Make-to-order) and select corresponding Invidual/collective indicator
- B. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Mixed MRP indicator
- C. Choose planning strategy 20 (Make-to-order) and select corresponding Mixed MRP indicator
- D. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Invidual/collective indicator
Answer: D
NEW QUESTION 45
You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?
- A. Specify a positive planning horizon in the strategy profile.
- B. Specify a positive offset time in the strategy profile.
- C. Specify a negative lanning horizon in the strategy profile.
- D. Specify a negative offset time in the strategy profile.
Answer: D
NEW QUESTION 46
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?
- A. Assign planned orders manual lying the planning table.
- B. Run MRP with automatic selection of production version.
- C. Run PP/DS heuristics for repetitive manufacturing.
- D. Run MRP with quota arrangement.
Answer: C,D
NEW QUESTION 47
You want to use capacity availability checks for production orders. Which settings have to be made for this?
- A. The Relevant for Finite Scheduling indicator must be set
- B. The PRT Availability Check must be set in the checking control.
- C. A checking rule must be assigned in the checking control
- D. An overall profile must be assigned in the checking control.
Answer: A,D
NEW QUESTION 48
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
- A. Purchase requistion
- B. Production order
- C. Planned order
- D. Scheduling agreement schedule line
- E. Stock transport order
Answer: A,C,D
NEW QUESTION 49
When do you use variant bills of materials (BOMs)?
- A. When a material has a configurable BOM
- B. When multiple materials have multiple BOMs
- C. When multiple materials also have similar BOMs
- D. When a material has multiple BOMs
Answer: B
NEW QUESTION 50
For a production version to be valid and consistent what requirements must be fulfilled?
- A. The assigned routing must NOT have alternative sequences.
- B. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- C. The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
- D. The lot size range must be within the lot-size range of the assigned routing.
- E. The assigned routing must be a rate routing.
Answer: B,C,D
NEW QUESTION 51
What is a work center hierarchy in planning in SAP S/4HANA?
- A. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
- B. A group of alternative work centers for production, structured in hierarchy levels by priorities
- C. A group of work centers in a production line being used in sequence for production
- D. A group of alternative work centers providing a cumulative available capacity for production.
Answer: D
NEW QUESTION 52
Which of the following processes lead to an entry in the MRP planing file?
- A. Change of the material's procurement type
- B. Change of the storage bin
- C. Creation of purchasing contract
- D. Creation of sales order
- E. Creation of dependent requirements
Answer: A,D,E
NEW QUESTION 53
You need to model goods receipt processing time in detailed scheduling. Whic modeling options do you have?
- A. Model a resource inbound in the location master.
- B. Model a handling resource in the location master and goods receipt time in the material master.
- C. Model a transportation resorce in the location master.
- D. Model a seperate resource in the production data structure.
Answer: B,C
NEW QUESTION 54
You are working with planning strategy 40 (Planning-with-final assembly) When does consuption of planned independent requirements take places?
- A. When you create a planned order
- B. When you create a sales order
- C. When the MRP result are saved
- D. When you deliver a sales order
Answer: B
NEW QUESTION 55
What type of time element can be reduced by strategy settings while dispatching?
- A. Transportation time
- B. Setup time
- C. Queue time
- D. Wait time
Answer: C,D
NEW QUESTION 56
......
C_TS422_2021 Exam Certification Details:
| Sample Questions: | SAP C_TS422_2021 Exam Sample Question |
| Languages: | German, English, Japanese, Chinese |
| Level: | Associate |
SAP C_TS422_2021 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Advanced Planning in SAP S/4HANA > 12% | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts |
| Process Orders in SAP S/4HANA < 8% | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). |
| Lean Manufacturing in SAP S/4HANA 8% - 12% | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. |
| Capacity Planning in SAP S/4HANA 8% - 12% | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. |
| Demand Management in SAP S/4HANA < 8% | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. |
| Master Data in SAP S/4HANA > 12% | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. |
Easy Success SAP C_TS422_2021 Exam in First Try: https://testinsides.vcedumps.com/C_TS422_2021-examcollection.html