With the aim of passing exams and get the related Microsoft certificate successively, exam candidates have been searching the best exam materials in the market to get the desirable outcome eagerly. We are here to offer help. You do not need to be confused anymore, because our 070-178 learning materials have greater accuracy compared with same-theme products. So once people make allusions to effective exam materials, we naturally come into their mind. To realize your dreams in your career, you need our 070-178 exam resources. Now, let us take a look of it in detail:
Concrete contents
We always improve and enrich the contents of the 070-178 practice test questions in the pass years and add the newest content into our 070-178 learning materials constantly, which made our 070-178 exam resources get high passing rate about 95 to 100 percent. So there is not amiss with our 070-178 practice test questions, and you do not need spare ample time to practice the 070-178 learning materials hurriedly, but can pass exam with least time and reasonable money. To clear your confusion about the difficult points, our experts gave special explanations under the necessary questions. That means our 070-178 exam resources are inexpensive in price but outstanding in quality to help you stand out among the average. So you will not squander considerable amount of money on our materials at all, but gain a high passing rate of 070-178 practice test questions with high accuracy and high efficiency, so it totally worth every penny of it.
High-quality exam materials
Our exam materials are of high-quality and accurate in contents which are being tested in real test and get the exciting results, so our 070-178 exam resources are efficient to practice. With around 20-30 hours practicing process, you will get the desirable grades in your Microsoft 070-178 exam. The most important one, we always abide by the principle to give you the most comfortable services during and after you buying the 070-178 practice test questions. Furthermore, the 070-178 learning materials will help you pass exam easily and successfully, boost your confidence to pursue your dream such as double your salary, get promotion and become senior management in your company. What are you waiting for, just go for our 070-178 exam resources.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Customer first principles
With the high passing rate of the 070-178 learning materials and solid relationship with customers, we build close relationship with clients. Our sincere and patient aftersales service is obviously our feature remembered by them for a long time since they finished payment on 070-178 exam resources. We never meet your needs with aloof manner but treat every customer seriously like families. Because different people have different buying habits, so we designed three versions of 070-178 practice test questions for you. All of them are usable with unambiguous knowledge up to now and still trying to edit more in the future (070-178 learning materials). All these considerations are being added to our services with the Customer first principle as our culture aims.
Microsoft 070-178 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Tracking and Controlling Projects | 25% | - Monitor schedule and costs
|
| Topic 2: Viewing and Reporting Project Data | 20% | - Customize views and tables
|
| Topic 3: Configuring and Automating Projects | 10% | - Work with multiple projects
|
| Topic 4: Managing Resources and Assignments | 25% | - Resolve resource conflicts
|
| Topic 5: Creating a Project Plan | 20% | - Create task relationships
|
Microsoft Project 2010, Managing Projects Sample Questions:
Question 1
Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?
A. Assign Resources
B. Clear Leveling
C. Level All
D. Resource Pool C Share Resources
Question 2
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
A. Select the Summary Tasks option.
B. Update the project calendar.
C. Create a manually scheduled summary task.
D. Select the Project Summary Task option.
Question 3
You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
A. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
B. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
C. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
D. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
Question 4
You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?
A. Use the Save Views feature.
B. Use the Organizer tool.
C. Use the Compare Projects feature.
D. Use the Links Between Projects tool.
Question 5
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A. Change the working time for the resource.
B. Change the maximum units for the resource.
C. Assign the resource only to tasks that are scheduled on the working days.
D. Update the base project calendar.
Solutions:
| Question 1 Answer: C | Question 2 Answer: C | Question 3 Answer: C | Question 4 Answer: B | Question 5 Answer: A |